Candlewood Suites on Redstone Arsenal in Huntsville, AL.
Built by LendLease
Previous Best Job
Steel |
Redstone Job
CLT Panels |
|
Gross SF | 54,891 | 62,688 |
Avg # Employees | 18 (Peak-26) | 10 (Peak-11) |
Structural Duration | 123 Days | 78 Days |
Man Hours | 14,735 | 8,203 |
Production Rate | 460 sf/day | 803 sf/day |
Overall Schedule | 15 Months | 12 Months |
.
* Raw cost neutral with steel *
.
37% faster
31% more energy efficient
Sequestered 1,656 tons of CO2
.
.
These numbers were provided by LendLease
.
.
Carbon Sequestration: Short, Sweet, by the Numbers